Date of Approval: 6.12.22
Administrative Approval: 13.1.23
Gestation Period: 1.1.23-31.12.28 (6 Years)
Status: Foreign Funded
- AA issued on 13.1.23
- Project became active on 15.2.23
- PIU established vide notification dated 2.1.23. Advertisement of recruitment published in Newspaper.
- C&W Deptt. has been requested to start work on COE’s.
- Hiring of Staff 933 officers / officials) completed.
- Office Building and vehicles have been procured, whereas Furniture and other items will be procured soon.
- Detailed Drawings and Technical Sanction received from C&W on 12th August
- Bidding Document completed
- Proposal shared with ADB to start two COEs (IST Sialkot and CAMI Mianchannu) as a pilot as these do not require Civil Works.
- Formal concept note alongwith proposed procurement plan will be shared with ADB31-08-2023
- Non-key staff recruited.
- Activities linked with the skills mapping exercise to be conducted under JFPR and will start after receipt of the report.
- Hiring of MIS Consultants for preparation of Database and MIS System has been started
- Procurement of furniture and equipment under process