• STATUS: FOREIGN FUNDED
• The PC-I is recommended by PDWP in its meeting held on 21.10.2022 and approved by CDWP in its meeting held on 24.03.2023. Administrative Approval issued on 07.06.2023 by ICI&SDD.
• The project will be executed in the light of these agreements and in close coordination with Implementing Consultant (IC) to be hired by KFW Development Bank, Germany.
• P&D released 50% funds on 24.8.2023. Matter taken up with FD for release of funds
• The PC-I is recommended by PDWP in its meeting held on 21.10.2022 and approved by CDWP in its meeting held on 24.03.2023. Administrative Approval issued on 07.06.2023 by ICI&SDD.
• The project will be executed in the light of these agreements and in close coordination with Implementing Consultant (IC) to be hired by KFW Development Bank, Germany.
• P&D released 50% funds on 24.8.2023. Matter taken up with FD for release of funds
Category
Foreign Funded Scheme