DATE OF APPROVAL: Original: 25.9.19
1st Revised: 20.10.20
2nd Revised: 29.4.22 (extension)
3rd Revised: 5.8.22 (extension)
ADMINISTRATIVE APPROVAL:
Original: 3.10.19
1st Revised: 12.11.20
2nd Revised: 29.4.22
GESTATION PERIOD:
Original: 1.7.19 to 30.6.21 (2 years)
1st Revision: 1.7.19 to 30.6.22 (3 years)
2nd Revision: 1.7.19 to 31.12.22 (3.5 years)
3rd Revision: 1.7.19 to 30.4.23 (3 years and 9 months)
STATUS: CLOSING ON 30.06.24, SLOW MOVING SCHEME
• Office building acquired. Staff appointed. Office equipment, IT equipment and Furniture & fixture procured.
• Training of 5th Batch (20 incubatees) started on 21.11.2022.
• First time extension in gestation period till 31.12.22 at the same cost & scope approved on 29.4.2022.
• Second time extension in gestation period till 30.04.2023 at the same cost & scope approved on 05.08.2022
• Revised PC-I has been submitted to ICI&SDD. And DDSC meeting was held on 07.04.2023 and the scheme has been further extended upto 30.06.2024 with revised scope and cost.
• PC-I was amended in light of minutes of DDSC and circulated 21.06.2023 for implementation of the scheme.
• Training of 6th batch has been started from 16.06.2023 and will be completed on 15.09.2023.
• Enrollment process for 7th Batch has been started. Training of 7th Batch will start from 01.10.2023.